IMPLEMENTATION

CONSTRUCTION OF INDUSTRIAL WASTEWATER PRE-TREATMENT PLANT IN SOSNOWIEC

CATEGORY: Inżynieria środowiska
STATUS: W trakcie realizacji

It will be the fourth such investment in Poland. More than that, the BIGGEST one! T4B in cooperation with T4B Ekotechnologie will build a wastewater pre-treatment plant in Sosnowiec.

As part of the order for MPGO Sp. z o.o., we will design and build a wastewater pre-treatment plant from comprehensive waste management – the biological part of waste processing and municipal landfills.
It will be the fourth pre-treatment plant in Poland based on the best possible wastewater treatment technology (MBR) and at the same time the largest. For T4B Ekotechnologie this is the third project built over the last few years in cooperation with WEHRLE company, which is the world leader in environmental protection.
The throughput of the plant will amount to 240 m3/d and will be made entirely in Lightweight building, consisting of closed bioreactors (denitrification and nitrification), separate ultrafiltration and nanofiltration/reversion osmosis system together with an automated washing and cleaning system. The solutions designed will ensure that bioaerosol and odour emissions are reduced by using appropriate solutions.
The technology will be adapted to changing weather conditions and is intended to provide an economical solution for continued operation

CONTRACT VALUE: over PLN 19 million gross
COMPLETION TIME: 11/2019 – 12/2021