IMPLEMENTATION

KOMOROWICE WASTEWATER TREATMENT PLANT IN BIELSKO-BIAŁA

CATEGORY: Inżynieria środowiska
STATUS: Zrealizowane

Works carried out under the sub-contractor agreement concluded with Stalbudom and Envirotech Sp. z o.o. (General Contractor) of the investment project entitled “Construction of a wastewater treatment plant for the treatment of leachate from fermented sludge dewatering in the side line of the Komorowice wastewater treatment plant in Bielsko-Biała” with a daily capacity of Q = 400 m3/d.

SUBJECT OF THE ORDER: Earthworks for the construction of a reinforced concrete tank and sewage system together with delivery and installation of the necessary elements and activities to protect the already existing tanks at the Komorowice wastewater treatment plant in Bielsko Biała

LOCATION: Komorowice

COMPLETION TIME: Q1.2019

 

 

 